PennDOT officials say construction is moving ahead of schedule on Route 581.

The westbound lanes of Route 581 were closed over the weekend as construction crews placed sections of a new bridge over 10th Street.

According to PennDOT, the bridge may open Sunday night or as early as Sunday afternoon. The work was expected to completed by 6 a.m. Monday.

In the meantime, northbound I-83 motorists headed to Route 581 should use the Capital Beltway and continue on I-83 through Harrisburg to I-81 South, to Route 581 East.

Southbound I-83 motorists headed to Route 581 West will use Exit 40-B to Carlisle Road, to 18th Street, to Hummel Avenue, to State Road, to Gettysburg Road, to Simpson Ferry Road, to Lower Allen Drive, to Route 15 North, to Route 581 West.

Drivers may want to consider using the Turnpike or other alternate routes.

Eastbound drivers will encounter a left-lane restriction and intermittent traffic stoppages as sections of the existing bridge are removed and the new bridge deck is set into place.

A local 10th Street detour follows Lowther Street, 3rd Street and Hummel Avenue.

The new bridge will use shallower steel girders to raise the the clearance on 10th Street from 13 feet, 11 inches to 14 feet, 7.5 inches. It will replace a bridge built in 1958.

The $22.1 million project is scheduled for completion this summer.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s